Educational Webinar: Snowy 2.0 – Marica Road West HDD: Innovation in Extreme Terrain

  • Home
  • Announcements
  • Educational Webinar: Snowy 2.0 – Marica Road West HDD: Innovation in Extreme Terrain
Title: Snowy 2.0-Marica Road West HDD: Innovation in Extreme Terrain  
Date & Time: 2 September 2026, 14:00-15:00 GMT (16:00-17:00 CEST / 10:00-11:00 EDT)  
Project Location: Australia  

Speakers:

Bryce Morrow, Michels Corporation      
Glenn Duyvestyn, Michels Corporation      

 
Fee & Recording Free of charge. Recording is available only to ISTT members.  The presentation file will be available for purchase for $10 for non-members and free for ISTT members.  
Registration Form →
2025 Istt No Dig2

This project won the ISTT's No-Dig Award in 2025 - Project Category.

Overview

Michels, an internationally operating contractor in trenchless construction, was asked in 2023 to complete the installation of a critical, extremely complex HDD for the Snowy 2.0 Pumped Hydro Project in New South Wales, Australia.

The Marica Road West HDD was necessary for the installation of power, water, and communication cables required to build and operate Snowy 2.0, the largest committed renewable energy project in Australia.

Stretching from Lobs Hole to Marica, the Marica Road HDD is 2,248 meters long, an impressive, yet not exceptional, length for a trenchless project.

However, the HDD borehole included an elevation difference of 600 meters from low side to high side, a configuration never achieved by HDD.

This installation method was deemed to be the best option for the successful installation of a 219-mm (8 5/8-inch) diameter fiberglass reinforced polymer (FRP) carrier pipeline and its critical cables in an environmentally significant area.

This presentation explores the technical challenges, innovative solutions, and lessons learned from the project, which was completed between April and July 2023.

Snowy 2.0 Marica Road West Terrain Profile HDD Borehole Pipeline Installation

Speakers

Bryce Morrow

Bryce Morrow

Michels Corporation

Bryce Morrow is General Manager at Michels Trenchless Pty. Ltd. in Australia, bringing extensive experience in trenchless technology and horizontal directional drilling projects. Based in Wangaratta, Victoria, Bryce has been instrumental in the successful delivery of complex infrastructure projects, including the award-winning Snowy 2.0 HDD works.

Glenn Duyvestyn

Glenn Duyvestyn, PhD., PE, PEng

Michels Corporation

Glenn Duyvestyn, PhD., PE, PEng is Director of Alternative Delivery at Michels Corporation, where he oversees innovative trenchless technology solutions and project delivery strategies. With advanced professional credentials and engineering expertise, Glenn brings both technical depth and strategic leadership to complex infrastructure projects across North America and internationally.

Education Logo Images

Contact With Us
Get Contact
  • E-mail: info@istt.com
Newsletter

40,000+ Trenchless Technology Professionals are subscribe Around the World. Do not be shy, subscribe !


Copyright © 2026 ISTT All Rights Reserved

Powered by
Multiple Translation is Powered by